Project overview*

EIS status EIS active
Description Open-cut coal mine with a yield of up to five million tonnes per annum of thermal coal; and associated infrastructure.
Proponent Cockatoo Coal Limited
Location/s Surat Basin, 12 km north-east of Wandoan and 340 km south-west of Rockhampton. Map
Local government/s Western Downs Regional Council
Investment $650 million
Key features
  • open-cut coal mine
  • coal handling and processing infrastructure
  • rail infrastructure, including a seven-kilometre rail spur connecting to the proposed Surat Basin Rail line
  • 23-kilometre high-voltage transmission line connecting to the proposed Wandoan substation
  • water supply pipeline from Wolleebee Creek to Glebe Weir or Dawson River  
Expected completion 2015
Jobs
  • 1000 (construction)
  • 400 (operational)

Have your say

The Coordinator-General has prepared draft terms of reference (TOR) for an environmental impact statement (EIS) for the North Surat-Collingwood Coal Project. The draft TOR set out the matters Cockatoo Coal Limited must address when preparing the EIS.

The public and state government advisory agencies are invited to comment on whether the draft TOR adequately cover all the matters the project proponent must address when preparing the EIS.

The Coordinator-General will consider your comments before finalising the TOR.

The project's impacts on matters of national environmental significance are being assessed under a bilateral agreement process.

Comments close at 5pm on Monday 28 May 2012.

How to comment

  1. Read the draft TOR
    • Download the draft terms of reference for EIS (PDF, 412 kB), or
    • view a printed copy between 30 April 2012 and 28 May 2012 at:
      • Miles Customer Service Centre, Western Downs Regional Council,
        29 Dawson Street, Miles
      • Wandoan Customer Service Centre, Western Downs Regional Council,
        6 Henderson Road, Wandoan
      • Wandoan Post Office, 11 Lawton Street,
      • State Library of Queensland, Cultural Centre, Stanley Place, South Bank, Brisbane.
  2. Comment
  3. Send your completed comment form to one of the following:
    • Email: collingwoodcoalproject@coordinatorgeneral.qld.gov.au
    • Post:
      The Coordinator-General
      C/- EIS project manager - North Surat-Collingwood Coal Project
      Significant Projects Coordination
      Department of State Development, Infrastructure and Planning
      PO Box 15517
      City East Qld 4002 Australia
    • Fax: +61 7 3225 8282

If you have special communication needs and wish to comment, telephone the EIS project manager on +61 7 3898 0508 to make alternative arrangements.

Read more about commenting on draft TOR.

Environmental impact statement (EIS) process

Date Activity
28 April 2012 to
28 May 2012
Public consultation on draft terms of reference for EIS (PDF, 412 kB).
22 March 2012 Project deemed a 'controlled action' by federal environment minister.
14 February 2012 Project referred to federal environment minister.
23 December 2011 Gazettal of 'significant project' declaration.
23 December 2011 Application, including initial advice statement (PDF, 2 MB), submitted.

Read more about the EIS process.

Media releases

Further information

For more information about the project, visit Cockatoo Coal's Surat Basin Projects web page.

* Project information supplied by proponent and subject to change.