| EIS status | Recommended project proceed subject to conditions and recommendations |
| Description | Open-cut coal mine with a yield of four million tonnes per annum (mtpa), and associated infrastructure. |
| Proponent | BHP Billiton Mitsubishi Alliance (BMA) Coal Operations. BMA is the manager and agent on behalf of the Central Queensland Coal Associates Joint Venture between BHP Billiton Ltd and Mitsubishi Development Pty Ltd. |
| Location/s | 30 km south-east of Moranbah, and about 170 km south-west of Mackay. Map |
| Local government/s | Isaac Regional Council |
| Investment | $1.6 billion |
| Key features |
|
| Expected completion | 2013 |
| Jobs |
|
Daunia Mine is one of the four components of the BMA Bowen Basin Coal Growth Project. The others are:
In total, the new and expanded mines will produce an extra 17.5 mtpa of coking coal for export.
Please note: Although all four components are covered in the same initial advice statement and terms of reference for the EIS, each component will be the subject of a separate EIS.
| Date | Activity |
|---|---|
| 26 October 2009 | Coordinator-General's report on EIS (PDF, 1.85 MB) released. |
| 3 April 2009 | Supplementary EIS submitted. |
| 29 November to 2 February 2009 |
Public consultation on EIS. |
| 6 November 2008 | Terms of reference for EIS (PDF, 500 KB) released. |
| 22 September 2008 | Project deemed a 'controlled action' by federal environment minister. |
| 28 August 2008 | Project referred to federal environment minister. |
| 9 August 2008 to 5 September 2008 |
Public consultation on draft terms of reference for EIS. |
| 18 July | Gazettal of 'significant project' declaration. |
| 27 May 2008 | Application, including initial advice statement (PDF, 1.1 MB), submitted. |
Read more about the EIS process.
Daunia coal mine project advances to next stage (2 November 2009)
For more information, visit BMA’s Growth Projects web page.