| EIS status | Recommended project proceed subject to conditions and recommendations |
| Description | A 373,662-megalitre dam, water from which will be transported via a 133 km pipeline to Moranbah and will primarily service coal mines (and associated communities) in Central Queensland’s coal basins. |
| Proponent | SunWater Ltd (a government-owned corporation) |
| Location/s |
|
| Local government/s | Isaac Regional Council |
| Investment | $1.17 billion |
| Key features |
|
| Expected completion | Mid-2014, subject to relevant approvals being granted for the project and commercial arrangements between Sunwater and customers. (The first filling is expected to occur during the 2014/2015 wet season.) |
| Jobs |
|
| Date | Activity |
|---|---|
| 20 January 2012 | Coordinator-General’s report on EIS released |
| 14 March 2011 | |
| 6 February 2010 to 22 March 2010 |
Public consultation on EIS |
| 16 July 2009 | Terms of reference for EIS (PDF, 314 KB) released. |
| 31 January 2009 to 9 March 2009 |
Public consultation on draft terms of reference for EIS. |
| 25 September 2008 | Project deemed a 'controlled action' by federal environment minister. |
| 28 August 2008 | Project referred to federal environment minister. |
| 7 March 2008 | Gazettal of ‘significant project’ declaration. |
| 20 February 2008 | Application, including initial advice statement (PDF, 528 KB), submitted. |
Read more about the EIS process.
Federal environment minister's approval of 'controlled action', subject to conditions.
For more information, visit the Connors River Dam and Pipelines webpage.
*Project information supplied by proponent and subject to change.