Alpha Coal Project

Project overview*

EIS status EIS active
Description Open-cut coal mine with an initial export capacity of 30 millions tonnes per annum (mtpa), supported by new rail and port infrastructure.
Proponent Hancock Coal Pty Ltd, Hancock Alpha West Pty Ltd and Hancock Coal Infrastructure Pty Ltd (joint proponents)
Location/s
  • Mine: Galilee Basin, 40 km north-west of Alpha, central Queensland
  • Rail corridor: from the mine site to the Port of Abbot Point
  • Port: Abbot Point (25 km north of Bowen)
Map
Local government/s
  • Barcaldine Regional Council (mine)
  • Barcaldine, Isaac and Whitsunday Regional Councils (rail corridor to Abbot Point)
  • Whitsunday Regional Council (Port of Abbot Point)
Investment $7 billion
Key features
  • 30 mt/a open-cut coal mine
  • 495 km railway
  • new port facility at Abbot Point
  • water and electricity infrastructure
Expected completion 2014
Jobs
  • 3820 (construction)
  • 2650 (operational)

Common user infrastructure

The railway and port will be designed to transport, load and ship the coal produced by the Alpha and Kevin's Corner mines but will be capable of being expanded to accommodate additional users.

The $7 billion investment in the Alpha Coal Project includes a $2.5 billion contribution towards this common user infrastructure ($1.5 billion for the rail and $1 billion for the port).

Environmental impact statement (EIS) process

Date Activity
21 November to
19 December 2011
Submitter and agency consultation on addendum to supplementary EIS
5 September to
3 October 2011
Submitter and agency consultation on supplementary EIS (SEIS)
5 November to
20 December 2010
Public consultation on EIS
1 June 2009 Terms of reference for EIS (PDF, 1.7 MB) released
7 February 2009 to
9 March 2009
Public consultation on draft terms of reference for EIS.
13 January 2009 Project deemed a ‘controlled action’ by federal environment minister.
11 December 2008 Project referred to federal environment minister.
24 October 2008 Gazettal of ‘significant project’ declaration.
18 September 2008 Application, including initial advice statement (PDF, 710 KB), submitted.

Read more about the EIS process.

Media releases

* Project information supplied by proponent and subject to change.